Stephanie Comon, Associate Civil Engineer for the
City of Torrance has provided the following
information on the street slurry seal program
which is underway in Southeast Torrance.
John Bailey, President
SETHA
Hi John,
Please see below link to the project website and
attached location map for the project.
For everyone’s reference, currently the
contractor is out in your neighborhood doing preparatory work ahead of the
slurry seal. This includes sealing cracks in the street and performing
localized dig-out repairs to deteriorated pavement (beginning Monday).
This work will take place over the next few weeks then slurry seal work will
follow.
During the preparatory work, parking will be
restricted however street closures are not anticipated, although traffic may
have to be temporarily detoured during intersection work.
Once slurry seal work begins notices will
be distributed to affected residents one week and two days
in advance, as that work does require each street to be closed for one day,
restricting access to and from each home’s driveway.
Schedule maps for the entire project will be uploaded on the
project website for anyone to view at any time.
Please let me know if you have any questions,
Stephanie Comon, P.E.
Associate Civil Engineer | City
of Torrance | Public Works Department
20500 Madrona Ave, Torrance, CA
90503 | www.torranceca.gov
scomon@torranceca.gov | 310.618.3079
voice | 310.781.6902 fax
Comments